Schedule
Week of August 3 — crews, inspections, deliveries, client meetings, deadlines, and follow-ups.
An inspection correction deadline was detected for Tuesday at noon.
From County Inspections email, Bayview Residence.
Move cabinet install from Friday to Monday.
Summit Cabinetry signals a likely 4-day delivery slip.
Add a pump truck confirmation call before Thursday's pour.
Garnet Ridge Lot 93 — no confirmation on file.
Monday
Framing crew — level 2
Bayview Residence
Crew · Crew A (6)
Client walkthrough
Garnet Ridge Lot 93
Client Meeting
Trim-out sequencing review
Moonshine Creek Retreat
Follow-Up
Tuesday
Framing re-inspection
Bayview Residence
Inspection
Permit revision due
Deep Creek Cabin Renovation
Deadline
Wednesday
Truss delivery
Garnet Ridge Lot 93
Delivery
Change order review
Garnet Ridge Lot 93
Client Meeting
Thursday
Concrete pour — foundation
Garnet Ridge Lot 93
Crew · Crew B (6)
Cabinet delivery
Bayview Residence
Delivery
Friday
Cabinet install
Bayview Residence
Crew · Finish Crew (3)
Engineer calc follow-up
Deep Creek Cabin Renovation
Follow-Up