Schedule

Week of August 3 — crews, inspections, deliveries, client meetings, deadlines, and follow-ups.

AI Schedule Recommendations

An inspection correction deadline was detected for Tuesday at noon.

From County Inspections email, Bayview Residence.

Move cabinet install from Friday to Monday.

Summit Cabinetry signals a likely 4-day delivery slip.

Add a pump truck confirmation call before Thursday's pour.

Garnet Ridge Lot 93 — no confirmation on file.

Monday

7:00 AMOn Track

Framing crew — level 2

Bayview Residence

Crew · Crew A (6)

1:00 PMOn Track

Client walkthrough

Garnet Ridge Lot 93

Client Meeting

4:00 PMCompleted

Trim-out sequencing review

Moonshine Creek Retreat

Follow-Up

Tuesday

12:00 PMAt Risk

Framing re-inspection

Bayview Residence

Inspection

3:00 PMWaiting

Permit revision due

Deep Creek Cabin Renovation

Deadline

Wednesday

8:00 AMOn Track

Truss delivery

Garnet Ridge Lot 93

Delivery

2:00 PMWaiting

Change order review

Garnet Ridge Lot 93

Client Meeting

Thursday

6:30 AMAt Risk

Concrete pour — foundation

Garnet Ridge Lot 93

Crew · Crew B (6)

10:00 AMDelayed

Cabinet delivery

Bayview Residence

Delivery

Friday

7:00 AMAt Risk

Cabinet install

Bayview Residence

Crew · Finish Crew (3)

11:00 AMWaiting

Engineer calc follow-up

Deep Creek Cabin Renovation

Follow-Up