Morning Briefing

Prioritized by schedule risk, then deadlines, client questions, vendor delays, and unanswered requests.

Good morning, Brian. The framing inspection at the Bayview project may be at risk tomorrow because the correction photos have not been sent to the inspector. I recommend assigning this to Kristen before 10:00 AM.

Two other items can turn into lost days: Thursday's concrete pour at Garnet Ridge has no confirmed pump truck, and Summit Cabinetry is signaling a four-day slip on the Bayview cabinet package. Sarah Whitmore has now asked twice about that delivery — a reply is drafted and waiting for your approval.

Immediate Attention

urgentBayview Residence

Framing inspection tomorrow at risk — correction photos not sent to inspector

Source
Email · County Inspections (Tue 4:42 PM)
Why it matters
A failed re-inspection pushes drywall by 5 working days and delays the client walkthrough.
Recommended action
Assign photo submission to Kristen before 10:00 AM
Owner & due
Kristen Doyle · Today, 10:00 AM
urgentGarnet Ridge Lot 93

Concrete pour scheduled Thursday with no confirmed pump truck

Source
Calendar + vendor thread with Kirkland Concrete
Why it matters
Crew of 6 is already scheduled; an unconfirmed pump means a full lost day.
Recommended action
Call Kirkland Concrete to confirm pump and backup slot
Owner & due
Marcus Reyes · Today, 12:00 PM

Today's Deadlines

highMoonshine Creek Retreat

Window submittal approval due to architect by 5:00 PM

Source
Email · Ridgeline Architecture
Why it matters
Order release depends on this approval; 9-week lead time starts on sign-off.
Recommended action
Review submittal and reply with approval
Owner & due
Brian Halverson · Today, 5:00 PM
mediumDeep Creek Cabin Renovation

Permit revision packet due to county

Source
Task from email · Deep Creek permitting
Why it matters
Missing today's cutoff adds a 2-week review cycle.
Recommended action
Upload revised packet
Owner & due
Alexis Nguyen · Today, 3:00 PM

Client Communication

highBayview Residence

Sarah Whitmore asked twice about Thursday cabinet delivery

Source
Email · sarah.whitmore@gmail.com (2 messages)
Why it matters
Repeated unanswered request; client has tied it to their move-in date.
Recommended action
Send drafted status reply with a confirmed update time
Owner & due
Brian Halverson · Today, 3:00 PM
mediumGarnet Ridge Lot 93

Client requested a tile change order estimate

Source
Email · Dan & Priya Kapoor
Why it matters
Change order pricing delays selections and the tile install window.
Recommended action
Draft estimate summary and pricing note
Owner & due
Tom Bradley · Tomorrow

Vendor and Material Updates

urgentBayview Residence

Summit Cabinetry flagged a possible 4-day delivery slip

Source
Email · dispatch@summitcabinetry.com
Why it matters
Cabinet install crew is booked Friday and would need rescheduling.
Recommended action
Confirm delivery window, hold crew tentatively
Owner & due
Kristen Doyle · Today, 2:00 PM
mediumMoonshine Creek Retreat

Plumbing fixtures backordered 3 weeks

Source
Vendor portal update · Cascade Supply
Why it matters
Trim-out sequencing needs a substitute or a schedule shift.
Recommended action
Request substitute options
Owner & due
Marcus Reyes · This week

Waiting on Others

mediumDeep Creek Cabin Renovation

Structural engineer has not returned beam calc — 4 days out

Source
Email thread · Larkin Engineering
Why it matters
Framing crew mobilizes Monday and cannot start without stamped calcs.
Recommended action
Send follow-up with a hard-need date
Owner & due
Alexis Nguyen · Today

Recommended Schedule Changes

highBayview Residence

Move cabinet install from Friday to Monday

Source
AI recommendation from vendor + crew data
Why it matters
Protects the crew day and absorbs the likely delivery slip without client impact.
Recommended action
Apply schedule change and notify crew
Owner & due
Kristen Doyle · Today