Moonshine Creek Retreat
77 Moonshine Creek Rd, Leavenworth, WA · Dry-in · PM Tom Bradley
On Track
Progress
44% complete
Next milestone: Window submittal approval — today
Open risks: 1
Client: Up to date
Vendor: Fixtures backordered
What TheBuildersOS is watching
high
Window submittal approval due to architect by 5:00 PM
Order release depends on this approval; 9-week lead time starts on sign-off.
medium
Plumbing fixtures backordered 3 weeks
Trim-out sequencing needs a substitute or a schedule shift.