Moonshine Creek Retreat

77 Moonshine Creek Rd, Leavenworth, WA · Dry-in · PM Tom Bradley

On Track
Progress

44% complete

Next milestone: Window submittal approval — today

Open risks: 1

Client: Up to date

Vendor: Fixtures backordered

What TheBuildersOS is watching
high

Window submittal approval due to architect by 5:00 PM

Order release depends on this approval; 9-week lead time starts on sign-off.

medium

Plumbing fixtures backordered 3 weeks

Trim-out sequencing needs a substitute or a schedule shift.