Bayview Residence
1420 Bayview Terrace, Gig Harbor, WA · Rough-in / Framing corrections · PM Kristen Doyle
62% complete
Next milestone: Framing re-inspection — Tue 12:00 PM
Open risks: 3
Client: Response needed
Vendor: Cabinet delivery delayed
Framing inspection tomorrow at risk — correction photos not sent to inspector
A failed re-inspection pushes drywall by 5 working days and delays the client walkthrough.
Sarah Whitmore asked twice about Thursday cabinet delivery
Repeated unanswered request; client has tied it to their move-in date.
Summit Cabinetry flagged a possible 4-day delivery slip
Cabinet install crew is booked Friday and would need rescheduling.
Move cabinet install from Friday to Monday
Protects the crew day and absorbs the likely delivery slip without client impact.